How Long Does a Kitchen Remodel Take in San Diego?

Thinking about giving your kitchen a fresh makeover in San Diego? Understanding the timeline is key to a smooth renovation. From planning and permits to installation and final walkthrough, here’s exactly what to expect—and when.

Planning and Design (2–4 Weeks)

Before demolition begins, a thorough planning and design process ensures your new kitchen functions beautifully and looks stunning.

  • Initial consultation and visioning: 1 week

  • Layout planning, consultations, and approvals: 1–2 weeks

  • Material selection (cabinets, countertops, fixtures): 1–2 weeks

If you want to upgrade your kitchen remodeling in San Diego with custom cabinetry, design coordination naturally adds a few extra days.

Permits and Approvals (3–8 Weeks)

Pulling permits in San Diego requires planning and city review. The timeline depends on project complexity:

  • Simple remodels (like cabinet surface updates): 3–4 weeks

  • Structural updates (moving walls, plumbing or gas lines): 6–8 weeks

Your general contractor and design team handle paperwork, submittals, and city follow-ups to avoid delays.

Demolition and Site Prep (1–2 Weeks)

Once permits are in hand, it’s time to safely demo:

  • Protect adjoining areas and install dust control: 1–2 days

  • Remove cabinets, appliances, flooring, and affected walls: 2–5 days

  • Prep the structure (check plumbing, electrical, framing): remaining time

Inspecting for unseen issues like water damage or framing concerns early helps avoid costly surprises.

Structural, Plumbing, and Electrical Rough-In (2–4 Weeks)

Now comes the heavy lifting behind the walls:

  • Framing or wall relocation: 1–2 weeks

  • Plumbing work: 3–7 days

  • Electrical updates and rewiring: 5–10 days

Coordination between trades is crucial—delays in one area can affect the whole timeline.

Inspections, Drywall, and Wall Prep (1–2 Weeks)

Once rough work is complete, inspections by city officials are required:

  • Scheduling and passing inspections: 3–7 days

  • Install drywall, tape, mud, sand, and prime: 4–7 days

Preparing walls properly now helps ensure a flawless finish later.

Cabinetry, Countertops & Fixtures (2–4 Weeks)

This is where your new dream kitchen starts taking shape:

  • Cabinet installation: 3–7 days

  • Countertop template, fabrication, and install: 1–3 weeks (depending on material like quartz or granite)

  • Fixture installation (sinks, faucets, lighting): 2–4 days

Exact timelines vary based on the availability of custom or specialty materials.

Backsplash, Painting & Flooring (1–2 Weeks)

The finishing touches bring it all together:

  • Backsplash tile installation and grouting: 3–7 days

  • Painting walls and trim: 2–4 days

  • Flooring installation: 3–7 days

Projects that rely on tile, especially hand-laid styles, may require more specialized labor time.

Final Touches & Punch List (1 Week)

Final checks ensure everything is up to standard:

  • Install hardware and adjust cabinets: 1–2 days

  • Final inspection walkthrough: 1–2 days

  • Touch-ups (paint, grout, hardware tweaks): 2–3 days

That finishes your new kitchen experience—and you’re ready to enjoy!

Typical Total Timeline

Combining all phases gives a typical timeline of:

  • Minimal remodels (surface-level updates without structural change): 8–10 weeks

  • Mid-range remodels (some structural, electrical, plumbing changes): 12–16 weeks

  • High-end or custom remodels (major layout change, custom cabinetry): 16–20 weeks or more

Factors That Affect Duration

Several variables can stretch or shorten your remodel timeframe:

  • Scope of work: Moving walls, plumbing, and major changes add time

  • Permit and city review delays: Allow buffer in your schedule

  • Material lead times: Custom cabinets, countertops, and fixtures may take weeks longer

  • Season and contractor availability: Off-season scheduling (November–February) tends to be faster

Tips to Keep Your Remodel on Track

  • Finalize designs before demo to ensure confidence in decisions

  • Order long-lead items early (e.g. cabinets, stone slabs)

  • Schedule inspections promptly after rough-ins are complete

  • Maintain clear communication with your contractor and trades

  • Plan for unexpected hiccups with a 10–15% time buffer

Why Choose a Professional Kitchen Remodel Team

A well-organized remodel goes beyond just time—it’s about experience, craftsmanship, and coordination.

  • Experienced teams anticipate delays and avoid costly missteps

  • They manage material sourcing to balance quality and lead times

  • They handle permit submittals and inspections efficiently

  • They coordinate all trades to avoid downtime and costly overlaps

The right remodel partner ensures your remodel finishes more quickly and with less stress—leaving you with a kitchen designed to last and delight.

Final Thoughts

If you’re dreaming of a beautiful new kitchen, expect the whole process in San Diego to take anywhere from two to five months, depending on complexity. Whether your goal is a kitchen upgrade or a full layout redesign, that timeline covers every step from concept to completion.